Oberstar is the prime contractor for this project, and the entire schedule includes:
Through April 18: Earth Excavation
Through April 23: Embankment Establishment
April 12-24: Sanitary Sewer Construction
April 23-May 1: Stream Channel Construction
April 24-May 1: Installation of Culvert Footings
April 25-May 16: Water Main Construction
May 2-8: Culvert Construction
May 9 (One Day Only): Stream Channel Diversion
May 17-30: Sanitary and Water Services Installation
May 31-June 18: Storm Sewer Construction
June 19-July 3: Road Sub-base Installation
July 25-August 21: Traffic Lighting
August 8-September 11: Concrete Curb, Sidewalk and Ramp Installation
September 12-19: Bituminous Paving
September 25: Road Striping